Our process

From your first email to handed keys: 4–7 months.

One contract. One project manager. One timeline. We coordinate factory and site so your project moves in parallel, not in sequence.

The seven steps

From your first email to handed keys.

1
5 business days

Free feasibility

Send us your property address, lot size, and what you're trying to build. Our team runs a desktop analysis: zoning eligibility, SB 1211 unit count (if multifamily), recommended Clever Elements or Clever Modular configuration, installed budget range, and timeline. We send back a PDF and offer a follow-up call.

Cost: free.
2
1–2 weeks

Site visit and engagement

If you want to move forward, we (or our local install partner) walk the site to verify utilities, access for delivery, soils, and any site-specific constraints. We sign an engagement letter for design-and-permit.

3
2–4 weeks

Schematic design and entitlement strategy

Our in-house architecture team designs the site plan and confirms unit configuration. We map the permitting path with your local jurisdiction and prepare the application package.

4
60 days+

Permit submittal

We submit the permit package. SB 1211 projects benefit from ministerial 60-day approval. Other project types follow your local jurisdiction's standard timeline.

Ministerial under SB 1211.
5
12 weeks

Factory build

Once permits are issued and your contract is fully executed, your units enter production at our Ensenada factory. You track build progress through your dedicated customer portal — same system used by 300+ prior customers.

6
Parallel

Site prep and foundations

While units are in the factory, our CA install partner pours foundations, runs underground utilities, and preps the site so install day is plug-and-play.

7
1–2 weeks

Crane install and final inspection

Units arrive on flatbed and install via crane in a single day per unit. Our team handles interior finish carpentry, final inspection coordination, and warranty registration. You take handoff.

What's in the price

One contract. One installed price.

Included

  • Site feasibility analysis
  • Schematic and permit-set design
  • Standard foundation and utility installation
  • Permitting management
  • Transportation up to 200 miles from the factory
  • Crane install
  • Interior finish carpentry
  • Final inspection coordination
  • 10-year structural warranty

Not included (scoped separately)

  • Unusual site work (heavy grading, retaining walls, special foundations)
  • Long-distance transport (>200 miles, ferries)
  • Utility extensions beyond standard
  • Local impact fees and inspection fees (vary by jurisdiction)
  • Furniture, finishes outside the standard package
Why we move fast

Factory and site work happen in parallel.

This is the time-saver. Stick-built crews work in sequence — foundation, framing, MEP, finish — one after another. We split them in half.

Phase
Mo 1
Mo 2
Mo 3
Mo 4
Mo 5
Mo 6
Mo 7
Feasibility + design
2–4 wks
Permitting (SB 1211)
60 days ministerial
Factory build
12 weeks
Site prep + foundations
Parallel
Crane install + finish
1–2 wks

Illustrative. Specific schedules confirmed during pre-construction.

Run the math on your project.

We'll send a free PDF feasibility analysis within 5 business days.